Accounting Procedures for Capital Improvement Projects
The local government accounting department should use a fund accounting system with general accounting, budgetary, and encumbrance features in order to account for capital projects.
When a contract is awarded, it should be encumbered against the authorized appropriations (budget), and when "change orders" are authorized, these should also be reflected in the accounting records. The procedures used should reflect the original approved amount for the project as a budget, the amount of contract as encumbered and any change orders for additional encumbrances, the amount paid to-date, the amount unpaid, and the unencumbered amount (available budget). Since capital projects often exceed the fiscal year, a manual accounting generally is required to reestablish the available budget and encumbrances after a fiscal year has been closed. The accountants may need to discuss specific posting with their auditors.
Status reports for the Capital Project Fund and related sub-funds should be prepared and distributed to the appropriate department heads and local legislative bodies as needed.
At stake in this process is the credibility for future projects.
Recommended Practice: File Capital Project Fund and sub-fund financial reports with the county legislative body at least quarterly for inclusion in the commission minutes. Financial credibility is at stake.